Change orders in construction
A change order is a signed amendment to the construction contract that changes its scope, price or schedule, and the owner pays for the changes it asks for and the risks the contract leaves with it, usually out of contingency. In the sample project, an illustrative $60,000 change order signed at month 10 cuts the contingency left to commit from $160,000 to $100,000 and, because the forecast had no room left under the budget, puts the project $60,000 over.
Updated
Who pays for a change order
The owner pays for changes it asks for: added scope, upgrades, a different layout. It also pays for the risks the contract leaves with it, which often include gaps in the owner's own drawings and site conditions nobody could see at bid. Under design-bid-build the owner hires the designer, so when the drawings miss something the contractor prices the fix as a change order and the owner pays it; design-build vs design-bid-build covers how each delivery method shifts that. The contractor pays for its own mistakes, its coordination, its means and methods, and any gap in its own price under a lump sum or a guaranteed maximum price.
A change order costs more than its price. The price is the direct cost of the work plus the markup the contract allows for overhead and profit. Then come the costs that do not appear on it: more weeks of the contractor's general conditions if it adds time, redesign and permit revisions on the soft cost side, and interest on the extra money and the longer schedule. Ask for the time impact in the same document as the price, because a change order signed with no time attached is hard to argue about later.
Worked on the sample budget
Suppose that at month 10 the owner asks for an upgrade worth $60,000, an illustration rather than anything in the sample. Book it where the work is: hard cost committed and forecast both rise by $60,000. Then move the same amount of budget from contingency to hard costs, so the hard cost line's own variance stays at the $110,000 it was already over, and contingency left to commit shows what the change used.
| Before | After the $60,000 change order | |
|---|---|---|
| Hard costs budget | $9,600,000 | $9,660,000 |
| Hard costs committed | $8,910,000 | $8,970,000 |
| Hard costs forecast | $9,710,000 | $9,770,000 |
| Contingency budget | $480,000 | $420,000 |
| Contingency left to commit | $160,000 | $100,000 |
| Forecast at completion over budget | $0 | $60,000 |
The change uses $60,000 of contingency, as expected. The total is the surprise. Before the change, the forecast at completion had no room left under the budget: the hard cost line was $110,000 over, and soft cost savings of $30,000 plus $80,000 of contingency the forecast did not expect to need had absorbed it. The contingency forecast of $400,000 also expected $80,000 more to be committed for changes still to come. So after the change, contingency left to commit says $100,000 remains while the forecast says the project is $60,000 over. Read the two together: contingency left is free money only once the forecast agrees.
Run through the pro forma as $60,000 more cost, the change adds $63,785 to total cost once interest is counted, and moves yield on cost from 6.62% to 6.60% and the levered IRR from 22.6% to 22.1%. The pro forma spreads the cost across the whole build, so the interest is an estimate. Feeding the budget's forecast back into the pro forma this way is the habit the pro forma vs budget guide argues for.
Change request vs change order
A change request is a proposal: either side asks for a change, the contractor prices it, and nothing is binding until both sign. Some contracts call it a proposed change order or a change order request. A change order is the signed result, and it changes the contract sum, the schedule or both. The difference matters in the budget. A request you expect to approve belongs in the forecast, so the overrun shows up early. A signed change order belongs in committed. Paying for work before its change order is signed puts money out with no signed contract behind it, and once payments on a line run ahead of its signed total the construction budget flags it: "Spent is more than committed: a payment has no signed contract behind it."
Deductive change orders
A deductive change order takes scope out and reduces the contract sum, so the credit runs to the owner. Price it as carefully as an addition: the contractor prices the deleted work, and some contracts allow overhead and profit on additions but give no matching credit on deletions. In the budget, a deduction lowers committed and forecast on its line; move the saving back into contingency with a budget transfer so it stays visible. Value engineering after a contract is signed usually arrives as a deductive change order, and the value engineering guide shows what a saving is worth to the returns.
Where the free budget stops
ProformaKit has no change order log, approval workflow or signatures. In the construction budget, a change shows up as the change to committed and forecast on its line, with the budget moved from contingency. Keep the log itself, with each change's number, date, amount, time impact and status, in a separate sheet, and reconcile its signed total to the committed column every month. How much contingency to carry in the first place is in the construction contingency guide.
Questions
What is the difference between a change request and a change order?
A change request is a proposal: one side asks for a change and the contractor prices it, but nothing is binding. A change order is the signed agreement that changes the contract's scope, price or time. In the budget, requests you expect to approve go in the forecast; signed change orders go in committed.
What is a deductive change order?
A change order that removes scope and reduces the contract sum, so the credit runs to the owner. Check how the contract prices credits, since some allow markup on added work but give no matching credit on deleted work.
Who pays for change orders in construction?
The owner pays for changes it asks for and for risks the contract leaves with it, such as errors in the owner's drawings or hidden site conditions. The contractor pays for its own mistakes and for gaps in its own price under a lump sum or guaranteed maximum price.
How do I type up a change order?
Include the contract and change number, a description of the change and the reason for it, the price broken into labor, materials, subcontracts and markup, the contract sum before and after (original, earlier changes, this change, new total), the change in contract time, and signature lines for the owner and contractor, plus the architect if the contract requires one.
Does a change order change the construction loan draws?
It adds to the cost the draws fund. If contingency that was already in the loan budget pays for it, the loan amount stays the same and the money moves between lines. If contingency cannot cover it, the extra falls on the equity unless the lender agrees to lend more.